American coastal defence submarine USS N-7 (1915-1922) on 1 September 1915


The No. 59. Lake. Building approved in 1915. First material immediately ordered. Keel laid after 2 months. After 6,5 months yet for 32% completed. Contracted building time 27 months.

Note
1. Laid down at the shipyard of Lake Torpedo Boat, Bridgeport, Connecticut, USA on 20 April 1915, launched on 19 May 1917 and commissioned on 15 June 1918.

Source
Marineblad 1915/1916 no. 6. The article was mainly based on a report of the Secretary of Navy dated 16 October 1915 over the year ending on 30 June 1915.