Displacement 390
(surfaced)-530 (submerged) tons, building allowed in 1913, first material
ordered after 2 months, keel laid down after 13,5 months, after 32 months of
building completed on 1 September 1915 for 98%. Contracted building time 24
months so she will at least 1 year too late be delivered.(1)
Note
1. Laid down at the shipyard
of the Fore Shipbuilding Company, Quincy, Massachusetts, USA on 19 March 1914,
launched on 11 February 1915 and commissioned on 28 November 1933.
Source
Marineblad 1915/1916
no. 6. The article was mainly based on a report of the Secretary of Navy dated
16 October 1915 over the year ending on 30 June 1915.