American coastal defence submarine USS N-4 (1915-1922) on 1 September 1915

The No. 56. Lake. Building approved in 1915. First material immediately ordered. Keel laid after one month. After 6,5 months yet for 34% completed. Contracted building time 24 months.

Note
1. Laid down at the shipyard of Lake Torpedo Boat, Bridgeport, Connecticut, USA on 24 March 1915, launched on 27 November 1916 and commissioned on 15 June 1918.

Source
Marineblad 1915/1916 no. 6. The article was mainly based on a report of the Secretary of Navy dated 16 October 1915 over the year ending on 30 June 1915.