Contractor. Bethlehem Steel Corporation, Fore River Shipyard, Quincy, Massachusetts, USA.
Percentage of completion on 1 May 1942: 14.5
Percentage of completion gain for April 1942: 1.1
Number of months between keel laying and completion: 22
Date of completion as per contract or order: 1 September 1944
Date of completion as reported by building yard on 11 January 1941: 15 August 1944
Date of completion as last reported by building yard: 1 September 1944
Months ahead/behind 11 January 1941 prediction:0.6 behind
Note
1. Part of Cleveland-class, preceded by Brooklyn-class, succeeded Fargo-class. Laid down on 13 February 1943, launched on 9 March 1944, commissioned on 9 September 1944, decommissioned on 30 September 1944, converted into a Providence-class guided missile cruisers Cleveland sub-class, preceded by Galveston-class, succeeded by Long Beach-class between 1957-1960, since 23 May 1957 classified as CLG-7, recommissioned 2 July 1960, decommissioned on 15 May 1974, classified as CG-7 on 1 July 1975, stricken on 31 July 1980 and sold to be broken up on 11 March 1980.
Sources
Franklin Roosevelt D. Roosevelt Presidential Library&Museum. Bureau of Ships: reports 1 May 1942 FDR’s President’s Secretary’s Files (psfc000095).