Contractor: Bethlehem Shipbuilding Corporation, San Francisco, USA.
Percentage of completion on 1 May 1942: 22.9
Percentage of completion gain for April 1942: 6.9
Keel laid on 1 August 1941.
Number of months between keel laying and completion: 23
Date of completion as per contract or order: 9 August
1943.
Date of completion as reported by building yard on 11
January 1941: 1 July 1943,
Date of completion as last reported by building yard: 1
July 1943
Months ahead/behind 11 January 1941 prediction: 0
Note
1. Of the Atlanta-class, modified design some times
called Oakland-class, preceded by Brooklyn-class regarded the machinery not
armament and succeeded by Juneau-class. Laid down on 1 August 1941, launched on
23 December 1942, commissioned on 28 December 1943, decommissioned on 4
November 1946, reclassified CLAA-96 on 18 March 1949, stricken on 1 March 1949
and sold to be broken up on 22 March 1962.