Tuesday 7 February 2023

Completion status of the American destroyer USS Terry (DD-25) on 30 June 1911

Name superintending constructor T.G. Roberts, contract signed on 13 October 1908, expiration of contract period on 13 October 1910, lines faired on 26 September 1908, first hull material ordered on 8 October 1908, keel laid down on 8 February 1909, first frame erected on 15 February 1909, first large castings received on 8 March 1909, first large castings erected on 20 March 1909, first compartment tested on 14 July 1909, launched on 21 August 1909, dock trial 3 September 1910, official trail 19 September 1910, estimated degree of completion on 30 June 1911, delivered to the government on 12 October 1910 and first commissioned on 18 October 1910.

Note

1. Part of modified Paulding-class, preceded by Smith-class, succeeded by Cassin-class. Built by Newport News Shipbuilding Company, Newport News, Virginia, USA, decommissioned on 13 November 1919, served within the Coast Guard 1924-1930, sold to be broken up on 2 May 1934 and stricken on 28 June 1934.

Sources

Annual reports of the Navy Department for the fiscal year 1911. Washington, 1912. Report of Chief Bureau of Construction and Repair dated 24 October 1911. The annual fiscal year ended 30 June 1911.

Warshipsresearchblogspot.com

No comments:

Post a Comment