Contractor. Bethlehem Steel Corporation, Fore River Shipyard, Bethlehem, USA.
Percentage of completion on 1 May 1942: 4.1
Percentage of completion gain for April 1942: 0.3
Number of months between keel laying and completion: 21
Date of completion as per contract or order: 14 September
1945
Date of completion as reported by building yard on 11
January 1941: 1 March 1945
Date of completion as last reported by building yard: 15
November 1944
Months ahead 11 January 1941 prediction: 3.5
Note
Of the Baltimore-class heavy cruisers, preceded by USS Wichita and succeeded by Oregon City-class. Building ordered on 9 September 1940, laid down on 28 June 1943, launched on 30 November 1944, commissioned on 8 June 1945, reclassified as CG-12 on 30 September 1959, decommissioned on 31 January 1975, stricken on 9 August 1976 and sold to be broken up on 3 October 1977.
Source
Franklin Roosevelt D. Roosevelt Presidential
Library&Museum. Bureau of Ships: reports 1 May 1942 FDR’s President’s
Secretary’s Files (psfc000095).