Contractor. New York Shipbuilding Corporation
Percentage of completion on 1 May 1942: 9.4
Percentage of completion gain for April 1942: 1.4
Number of months between keel laying and completion: 18
Date of completion as per contract or order: 30 December
1945
Date of completion as reported by building yard on 11
January 1941: 15 October 1944
Date of completion as last reported by building yard: 15
February 1944
Months ahead/behind 11 January 1941 prediction: ahead 8.0
Note
1. Part of Cleveland-class, preceded by Brooklyn-class,
succeeded by Fargo-class. Building ordered on 16 December 1940, to be completed
as an Independence-class light aircraft carrier, reclassified as CV-29 and
renamed Bataan on 2 June 1942, laid down on 31 August 1942, reclassified as
CVL-29 on 15 July 1943, launched on 1 August 1943, commissioned on 17 November
1943, finally decommissioned on 9 April 1954, stricken on 1 September 1959 and
sold to be broken up on 19 June 1961.