Contractor. Newport News Shipbuilding and Dry Dock Company, Newport News, Virginia, USA.
Percentage of completion on 1 May 1942: 67.4
Percentage of completion gain for April 1942: 7.1
Laid down: 17 February 1941
Launched: 20 March 1942
Number of months between keel laying and completion: 21
Date of completion as per contract or order: 3 March 1943
Date of completion as reported by building yard on 11 January 1941: 3 March 1943
Date of completion as last reported by building yard: 20 November 1942
Months ahead/behind 11 January 1941 prediction:ahead 3.4
Note
1. Part of Cleveland-class, preceded by Brooklyn-class, succeeded Fargo-class. Commissioned on 29 January 1943, decommissioned on 2 January 1947, stricken on 1 March 1959 and sold to be broken up on 12 November 1959.