Contractor: New York Shipbuilding Corporation, Camden, New
Jersey, USA.
Percentage of completion on 1 May 1942: 66.9
Percentage of completion gain for April 1942: 5.4
Laid down: 26 December 1940
Launched 4 April 1942
Number of months between keel laying and completion: 22.1/6
Date of completion as per contract or order: 27 September
1943
Date of completion as reported by building yard on 11
January 1941: 30 December 1943
Date of completion as last reported by building yard: 1
November 1942
Months ahead/behind 11 January 1941 prediction: ahead 13.9
Note
1. Part of Cleveland-class, preceded by Brooklyn-class,
succeeded Fargo-class. Commissioned on 15 October 1942, decommissioned on 7
February 1947, stricken on 1 March 1959 and sold to be broken up on 4 February
1960.