Contractor. Boston Navy Yard.
Percentage of completion on 1 May 1942: 99.8
Percentage of completion gain for April 1942: 1.3
Laid down: 6 January 1942
Launched: 14 June 1942
Number of months between keel laying and completion: 16
Date of completion as per contract or order: 12 April 1942
Date of completion as reported by building yard on 11 January 1941: 20 March 1942
Date of completion as last reported by building yard: 6 May 1942
Months ahead/behind 11 January 1941 prediction: behind 1.6
Commissioned: 3 February 1942.
Note
1. Part of Gleaves-class destroyers, preceded by Benson-class, succeeded by Fletcher-class. Commissioned on 3 February 1942, decommissioned on 24 February 1956, stricken on 1 July 1971 and sunk while used as a target off Florida, USA on 15 November 1973.