Building approved in 1913.
First material ordered after 0,5 month. Keel laid after 10 months. On 1
September after 1 year and 11 months 88% completed, will be at least 3 months
over time. Contracted building time 2 years.(1)
Note
1. Tucker class. Ordered in
1913. Laid down by New York Shipbuilding, Camden, New Jersey with yard number
150 on 3 August 1914, launched on 29 May 1916 and commissioned on 10 February
1916. Hull number DD-61.
Source
Marineblad 1915/1916
no. 6. The article was mainly based on a report of the Secretary of Navy dated
16 October 1915 over the year ending on 30 June 1915.