Wednesday 23 December 2015

American destroyer USS Wilkes (1915-1934) on 1 September 1915

Building approved in 1915. First material immediately ordered. On 1 September after 7 months 22% completed. Contracted building time 22 months. Displacement 1.100 tons.(1)

Note
1. Sampson-class. Laid down at William Cramp and Sons Ship&Engine Building, Philadelphia, USA on 11 March 1915, launched on 18 May 1916 and commissioned on 10 November 1916. Hull number DD-67.

Source
Marineblad 1915/1916 no. 6. The article was mainly based on a report of the Secretary of Navy dated 16 October 1915 over the year ending on 30 June 1915.