Translate

Wednesday 23 December 2015

American destroyer USS Davis (1915-1934) on 1 September 1915

Building approved in 1915. First material immediately ordered. Keel laid after 3 months. On 1 September after 7 months 44% completed. Contracted building time 22 months. Displacement 1.100 tons (1)

Note
1. Sampson-class. Laid down by Bath Iron Works, Bath, Maine, USA on 7 May 1915, launched on 15 August 1915 and commissioned on 5 October 1916. Hull number DD-65.

Source
Marineblad 1915/1916 no. 6. The article was mainly based on a report of the Secretary of Navy dated 16 October 1915 over the year ending on 30 June 1915.