American destroyer USS Rowan (1915-1939) on 1 September 1915

Building approved in 1914. First material immediately ordered. Keel laid after 5 months. On 1 September after 1 year and 8,5 months 43% completed. Contracted building time 2 years. Displacement 1.100 tons (1)

Note
1. Sampson-class. Laid down by the Fore River Shipbuilding Company, Quincy, Massachusetts, USA on 10 May 1915, launched on 23 March 1916 and commissioned on 22 August 1916. Hull number DD-64.

Source

Marineblad 1915/1916 no. 6. The article was mainly based on a report of the Secretary of Navy dated 16 October 1915 over the year ending on 30 June 1915.