Percentage of completion on 1 May 1942: 44.3
Percentage of completion gain for April 1942: 8.0
Baltimore-class
Oregon City-class
Number of months between keel laying and completion: 21-1/6
Date of completion as per contract or order: 14 June 1943
Date of completion as reported by building yard on 11
January 1941: 1 April 1943
Date of completion as last reported by building yard: 1
March 1945
Months ahead 11 January 1941 prediction: 1.0
Note
1. Of the Baltimore-class heavy cruisers, preceded by USS
Wichita and succeeded by Oregon City class, consisted of the Boston and Albany
sub-classes. Laid down on 26 May 1941, launched on 28 July 1942, commissioned
on 15 April 1943, last time decommissioned 31 May 1956, stricken 15 February
1971 and sold to be broken up on 10 April 1972 which was executed since
September 1972.