Contractor. Bethlehem Steel Corporation, Fore River Shipyard, Bethlehem, USA.
Percentage of completion on 1 May 1942: 30.9
Percentage of completion gain for April 1942: 5.2
Keel laid down on 3 September 1941
Number of months between keel laying and completion: 22
Date of completion as per contract or order: 14
December 1943
Date of completion as reported by building yard on 11
January 1941: 15 August 1943
Date of completion as last reported by building yard: 1
July 1943
Months ahead 1.51 January 1941 prediction: 1.5
Note
1. Of the Baltimore-class heavy cruisers, preceded by USS Wichita and succeeded by Oregon City class, consisted of the Boston and Albany sub-classes. Building ordered 1 July 1940, Laid down as USS Pittsburgh but during the building renamed USS Canberra, launched 19 April 1943, commissioned 14 October 1943, reclassified as CAG-2 while armed with guided missiles 4 January 1952, reclassified CA-70 1 May 1968, stricken 31 July 1978 and sold tob e broken up on 15 July 1980.
Sources
Franklin Roosevelt D. Roosevelt Presidential
Library&Museum. Bureau of Ships: reports 1 May 1942 FDR’s President’s
Secretary’s Files (psfc000095).