Baltimore-class
Oregon City-class
Contractor. Bethlehem Steel Corporation, Fore River Shipyard, Bethlehem, USA.
Percentage of completion on 1 May 1942: 39.5
Percentage of completion gain for April 1942: 5.2
Keel laid down on 30 June 1941
Number of months between keel laying and completion: 21-1/2
Date of completion as per contract or order: 14 August 1943
Date of completion as reported by building yard on 11
January 1941:
Date of completion as last reported by building yard: 1 June
1943
Months ahead 11 January 1941 prediction: 14 April 1943: 1.5
Note
Of the Baltimore-class heavy cruisers, preceded by USS Wichita and succeeded by Oregon City-class. Laid down on 30 June 1941, launched on 26 August 1942, commissioned on 30 June 1943, classified CAG-1 between 4 January 1952-1 May 1968, last time decommissioned on 5 May 1970, stricken on 4 January and sold to be broken up on 28 March 1975.