Percentage of completion on 1 May 1942: 91.4
Percentage of completion gain for April 1942: 11.0
Laid down: 1 July 1940
Launched: 1 November 1941
Number of months between keel laying and completion: 23
Date of completion as per contract or order: 23 March 1943
Date of completion as reported by building yard on 11
January 1941: 1 July 1942
Date of completion as last reported by building yard: 1 June
1942
Months ahead/behind 11 January 1941 prediction: 1 ahead
Note
1. Part of Cleveland-class, preceded by Brooklyn-class,
succeeded Fargo-class. Building ordered on 17 May 1938, hull number 423,
commissioned on 15 June 1942, decommissioned on 7 February 1947, stricken on 1
March 1959 and sold tob e broken up on 18 February 1960.