Contractor. Los Angeles Shipbuilding and Dry Dock Company, San Pedro, California, USA
Percentage of completion on 1 May 1942: 14.7
Percentage of completion gain for April 1942: 4.3
Keel laid: 9 March 1942
Number of months between keel laying and completion: 21½
Date of completion as per contract or order: 30 July 1944
Date of completion as reported by building yard on 11
January 1941: 1 January 1944
Date of completion as last reported by building yard: 15
December 1943
Months 11 January 1941 prediction: 0.6 ahead
Note
1. Of the Vulcan-class repair ships. Launched on 3 April 1943, commissioned on 19 June 1944, decommissioned and stricken on 24 June 1995, reclassified AR-8 on 9 September 1957and broken up in 2007.
Sources