Contractor. Los Angeles Shipbuilding and Dry Dock Company, San Pedro, California, USA
Percentage of completion on 1 May 1942: 53.2
Percentage of completion gain for April 1942: 7.6
Keel laid: 7 May 1941
Number of months between keel laying and completion: 25
Date of completion as per contract or order: 9 September
1943
Date of completion as reported by building yard on 11
January 1941: 10 May 1943
Date of completion as last reported by building yard: 10
June 1943
Months 11 January 1941 prediction: behind 1
Note
1. Of the Vulcan-class repair ships. Launched on 22 August
1942, commissioned on 30 October 1943, decommissioned on 31 December 1986,
stricken on 16 May 1989 and sold to be broken up on 23 May 1997.
Sources
Franklin Roosevelt D. Roosevelt Presidential
Library&Museum. Bureau of Ships: reports 1 May 1942 FDR’s President’s
Secretary’s Files (psfc000095).