Name superintending constructor H.S. Howard, contract signed on 19 January 1911, expiration of contract period on 19 September 1912, lines faired on 22 February 1911, first hull material ordered on 12 September 1910, keel laid down on 30 March 1911, first frame erected on 13 April 1911, first large castings received on 7 February 1911, estimated degree of completion on 30 June 1911 20.1%.(1)

Note

1. Part of G-class submarines, preceded by F-class, succeeded by H-class. Renamed G-3 on 17 November 1911, launched by Lake Torpedo Boat, Bridgeport, Connecticut, USA on 27 December 1913, commissioned on 5 May 1921, decommissioned on 5 May 1921, stricken and sold to be broken up on 19 April 1921.

Source

Annual reports of the Navy Department for the fiscal year 1911. Washington, 1912. Report of Chief Bureau of Construction and Repair dated 24 October 1911. The annual fiscal year ended 30 June 1911.