Contractor. Bristol Yacht Building Co. , South Bristol, Maine, USA
Percentage of completion on 1 May 1942: 95.0
Percentage of completion gain for April 1942: 10.0
Keel laid:27 August 1941
Launched: 2 April 1942
Number of months between keel laying and completion: 8 3/4
Date of completion as per contract or order: 12 November 1941
Date of completion as reported by building yard on 11 January 1941:
Date of completion as last reported by building yard: 4 May 1942
Months 11 January 1941 prediction: 0.5 behind
Note
1. Originally named Chief? Part of Accentor-class minesweepers, delivered to the US Navy on 18 May 1944, commissioned on 27 May 1942, decommissioned on 27 December 1945, stricken on 21 January 1946, handed over to the US Maritime Commission (Marcom) for disposal on 22 July.
Sources
Franklin Roosevelt D. Roosevelt Presidential Library&Museum. Bureau of Ships: reports 1 May 1942 FDR’s President’s Secretary’s Files (psfc000095).