Contractor. Hutchinson Boat Works, Alexandria Bay, New York, USA
Percentage of completion on 1 May 1942: 88.0
Percentage of completion gain for April 1942: 4.0
Laid down: 30 September 1941
Launched on 18 April 1942
Number of months between keel laying and completion:
Date of completion as per contract or order: 26 January 1942
Date of completion as reported by building yard on 11 January 1941: 29 April 1942
Date of completion as last reported by building yard: 20 June 1942
Months 11 January 1941 prediction: 1.7 behind
Note
1. Commissioned on 28 July 1942, handed over tot he Maritime Administration to be disposed on 28 July 1958.
Sources
Franklin Roosevelt D. Roosevelt Presidential Library&Museum. Bureau of Ships: reports 1 May 1942 FDR’s President’s Secretary’s Files (psfc000095).