Contractor. Elscot Boat Works Inc., Brooklyn, New York, USA
Percentage of completion on 1 May 1942: 75.0
Percentage of completion gain for April 1942: 5.0
Laid down: 18 September 1941
Date of completion as per contract or order: 26 January 1942
Date of completion as reported by building yard on 11 January 1941: 26 February 1942
Date of completion as last reported by building yard: 8 June 1942
Months 11 January 1941 prediction: 3.4 behind
Note
1. Commissioned in late July 1942, handed over to Peru and renamed Cardenas (API 171) in November 1958.