Translate

Tuesday 2 August 2022

Completion status of the American submarine USS Barracuda on 30 June 1911

Name superintending constructor C.W. Fisher, contract signed on 5 March 1909, expiration of contract period on 5 June 1911, contracted time extended to, lines faired on 2 June 1909, first hull material ordered on 26 April 1909, keel laid down on 23 August 1909, first frame erected on 31 august 1909, first large castings received on 23 February 1910, first large castings erected on 4 April 1910, first compartment tested on 31 March 1910, estimated degree of completion on 30 June 1911 90%.(1)

Note

1. SS-21. Part of the F-class submarines, preceded by E-class, succeeded by G-class, renamed USS F-2 on 17 November 1911, launched by Union Iron Works, San Francisco, USA on 19 March 1912, commissioned on 25 June 1912, decommissioned on 16 March 192 and sold on 17 August 1922.

Source

Annual reports of the Navy Department for the fiscal year 1911. Washington, 1912. Report of Chief Bureau of Construction and Repair dated 24 October 1911. The annual fiscal year ended 30 June 1911 

No comments:

Post a Comment