Name superintending constructor G.C. Westervelt, contract signed on 5 March 1909, expiration of contract period on 5 August 1911, lines faired on 30 June 1909, first hull material ordered on 15 April 1909, keel laid down on 17 August 1909, first frame erected on 16 September 1909, first large castings received on 20 April 1910, first large castings erected on 16 May 1910, first compartment tested on 20 April 1910, and estimated degree of completion on 30 June 1911 85.1%.(1)
Note
1. Part of F-class, succeeded by E-class, succeeded by G-class, renamed F-3 on 17 November 1911, launched by Moran Brothers, Seattle, Washington on 6 January 1912, commissioned on 5 August 1912, decommissioned on 15 March 1922 and sold on 17 August 1922.
Source
Annual reports of the Navy Department for the fiscal year 1911. Washington, 1912. Report of Chief Bureau of Construction and Repair dated 24 October 1911. The annual fiscal year ended 30 June 1911.