Name superintending constructor L. Bankson, contract signed on 31 May 1911, expiration of contract period on 30 June 1913, estimated degree of completion on 30 June 1911 0.0%.

Note

1. Part of K-class, preceded by H-class, succeeded by L-class, laid down by Fore River Shipyard, Quincy, Massachusetts, USA on 20 February 1912, launched on 4 October 1913, commissioned on 31 January 1914, renamed K-3, reclassified as SS-33 on 17 July 1920 and sold to be broken up on 3 June 1931.

Source

Annual reports of the Navy Department for the fiscal year 1911. Washington, 1912. Report of Chief Bureau of Construction and Repair dated 24 October 1911. The annual fiscal year ended 30 June 1911.