Baltimore-class
Oregon City-class
Contractor. Bethlehem Steel Corporation, Fore River
Shipyard, Bethlehem, USA.
Percentage of completion on 1 May 1942: 4.1
Percentage of completion gain for April 1942: 0.4
Number of months between keel laying and completion: 22-1/2
Date of completion as per contract or order: 14 August 1945
Date of completion as reported by building yard on 11
January 1941: 15 January 1945
Date of completion as last reported by building yard: 1
October 1944
Months ahead 11 January 1941 prediction: 3.5
Note
1. Of the Baltimore-class heavy cruisers, preceded by USS
Wichita and succeeded by Oregon City-class. Laid down on 3 February 1943 as
Rochester, launched on 16 September 1944, commissioned on 17 February 1945 as
Saint Paul, decommissioned on 30 April 1971, stricken on 31 July 1978 and sold
to be broken up on 13 December 1879.