Contractor: New York Shipbuilding Corporation, Camden, New
Jersey, USA.
Percentage of completion on 1 May 1942: 84.2
Percentage of completion gain for April 1942: 9.5
Laid down: 19 August 1940 [18 August?]
Launched: 17 December 1941
Number of months between keel laying and completion: 22.5/6
Date of completion as per contract or order: 23 June 1943
Date of completion as reported by building yard on 11
January 1941: 1 September 1942
Date of completion as last reported by building yard: 15
July 1942
Months ahead/behind 11 January 1941 prediction: 1.6 ahead
Note
1. Part of Cleveland-class, preceded by Brooklyn-class,
succeeded Fargo-class. Commissioned on 29 July 192, decommissioned on 30
November 1946, stricken on 1 March 1959 and sold to be broken up on 18 February
1959.
Sources
Franklin Roosevelt D. Roosevelt Presidential
Library&Museum. Bureau of Ships: reports 1 May 1942 FDR’s President’s
Secretary’s Files (psfc000095).