Contractor: New York Shipbuilding Corporation, Camden, New
Jersey, USA.
Percentage of completion on 1 May 1942: 69.6
Percentage of completion gain for April 1942: 6.4
Laid down: 2 December 1940
Launched 12 February 1942
Number of months between keel laying and completion: 2202/5
Date of completion as per contract or order: 27 June 1943
Date of completion as reported by building yard on 11
January 1941: 1 November 1942
Date of completion as last reported by building yard: 15
September 1942
Months ahead/behind 11 January 1941 prediction: 1,5 ahead
Note
1. Part of Cleveland-class, preceded by Brooklyn-class,
succeeded Fargo-class.Laid down on 2 December 1940, launched on 12 February
1942, commissioned on 9 September 1942, decommissioned on 24 January 1947,
stricken on 1 March 1959 and sold to be broken up on 22 January 1960
Sources
Franklin Roosevelt D. Roosevelt Presidential
Library&Museum. Bureau of Ships: reports 1 May 1942 FDR’s President’s
Secretary’s Files (psfc000095).