Contractor: New York Shipbuilding Corporation, Camden, New Jersey, USA.
Percentage of completion on 1 May 1942: 50.1
Percentage of completion gain for April 1942: 3.6
Laid down 7 June 1941
Number of months between keel laying and completion: 17.4/5
Date of completion as per contract or order: 16 January 1944
Date of completion as reported by building yard on 11
January 1941: 15 April 1943
Date of completion as last reported by building yard: 1
December 1942
Months ahead/behind 11 January 1941 prediction: 4.5 ahead
Note
1. Part of Cleveland-class, preceded by Brooklyn-class,
succeeded Fargo-class. Launched on 10 June 1942, decommissioned on 29 October
1946, stricken on 1 March 1959 and sold to be broken up on 9 November 1959.