Contractor. Newport News Shipbuilding and Dry Dock Company, Newport News, Virginia, USA.
Percentage of completion on 1 May 1942: 37.8
Percentage of completion gain for April 1942: 3.2
Laid down: 9 July 1941
Number of months between keel laying and completion: 22.2/5
Date of completion as per contract or order: 9 November 1943
Date of completion as reported by building yard on 11 January 1941: 3 September 1943
Date of completion as last reported by building yard: 21 May 1943
Months ahead/behind 11 January 1941 prediction: ahead 3.4
Note
1. Part of Cleveland-class, preceded by Brooklyn-class, succeeded Fargo-class. Laid down on 9 July 1941, launched on 23 February 1943, commissioned on 31 August 1943, decommissioned on 28 August 1946, stricken on 1 December 1951 and sold to be broken up on 5 March 1962.