American self-propelled 75 foot district patrol craft USS YP-81 according to the report of progress of naval construction dated 1 May 1942

Contractor. Elscot Boat Works Inc., Brooklyn, New York, USA 

Percentage of completion on 1 May 1942: 85.0 

Percentage of completion gain for April 1942: 5.0 

Laid down: 4 September 1941 

Launched: 4 April 1942 

Number of months between keel laying and completion:  

Date of completion as per contract or order: 26 January 1942 

Date of completion as reported by building yard on 11 January 1941: 4 February 1942 

Date of completion as last reported by building yard: 20 May 1942 

Months 11 January 1941 prediction: 3.5 

Note 

1. Contract awarded on 30 June 1941, delivered and commissioned on 15 June 1942, became in 1976 the private owned fishing vessel Pathfinder, since 1984 fate unknown.  