Contractor. Elscot Boat Works Inc., Brooklyn, New York, USA
Percentage of completion on 1 May 1942: 90.0
Percentage of completion gain for April 1942: 5.0
Laid down: 25 August 1942
Launched: 20 March 1942
Number of months between keel laying and completion:
Date of completion as per contract or order: 26 January 1942
Date of completion as reported by building yard on 11 January 1941: 19 January 1942
Date of completion as last reported by building yard: 14 May 1942
Months 11 January 1941 prediction: 3.8 behind
Note
1. Contract awarded on 30 June 1941, delivered and commissioned on 12 June 1942, handed over Haiti and renamed Indépendance (CG-12) in 1960.
Sources
Franklin Roosevelt D. Roosevelt Presidential Library&Museum. Bureau of Ships: reports 1 May 1942 FDR’s President’s Secretary’s Files (psfc000095).