Name superintending constructor C.W. Fisher, contract signed on 10 August 1910, expiration of contract period on 10 January 1913, lines faired on 9 December 1910, first hull material ordered on 7 December 1910, keel laid down on 22 March 1911, first frame erected on 1 April 1911, first large castings received on 19 April 1911, estimated degree of completion on 30 June 1911 34.1%.(1)
Note
1. Renamed H-1 on 17 November 1911, launched by Union Iron Works, San Francisco, USA on 6 May 1913, commissioned on 1 December 1913, run aground off the Magdalena Bay, Mexico on 12 March 1920, lost during her salvage on 24 March 1920 and stricken on 12 April 1920. Part of H-class submarines, preceded by G-class, succeeded by K-class.
Source
Annual reports of the Navy Department for the fiscal year 1911. Washington, 1912. Report of Chief Bureau of Construction and Repair dated 24 October 1911. The annual fiscal year ended 30 June 1911.