Completion status of the American submarine USS Salmon on 30 June 1911

Name superintending constructor L. Bankson, contract signed on 23 November 1907, expiration of contract period on 23 December 1909, contracted time extended to 11 August 1910, lines faired on18 January 1908, first hull material ordered on 3 December 1907, keel laid down on 16 April 1908, first frame erected on 2 May 1908, first large castings received on 6 April 1908, first large castings erected on 14 July 1908, first compartment tested on 27 November 1908, launched on 12 March 1908, dock trial on 8 April 1910, official trail between 9 and 18 June 1910, delivered to the government on 1 September 1910 and first commissioned on 8 September 1910.(1)

Note

1. Part of D-class submarines, preceded by C-class, succeeded  by E-class, built by Fore River Shipyard, Quincy, Massachusetts, USA, renamed D-3 on 17 November 1911, decommissioned on 29 March 1922 and sold to be broken up on 31 July 1922.

Source

Annual reports of the Navy Department for the fiscal year 1911. Washington, 1912. Report of Chief Bureau of Construction and Repair dated 24 October 1911. The annual fiscal year ended 30 June 1911.

No comments:

Post a Comment